At a glance
- Never under the load, never in the swing radius
- One signal person; everyone else stays out of it
- 20 feet from power lines unless the utility work rules say otherwise
- Taglines control loads — hands never do
Introduction
When a crane is working, the most dangerous places on site are directly under the load path and inside the swing radius — and both move. Crane incidents kill riggers, signal persons, and bystanders more often than operators. Most of us will never run a crane, but all of us work around them, so today's talk is about being ground crew: where to stand, who talks to the operator, and what the barricades actually mean.
The Zones
- The fall zone — anywhere the load or its parts could land — is a no-walk area; never cross under a suspended load, even moving quickly
- The swing radius of the counterweight is barricaded because it crushes; respect the barricade even when the crane looks idle
- Loads get rigged, lifted, and landed in controlled areas — if you're not part of the lift, you're outside them
- Watch overhead ANY time you hear the crane work; hard hat always in crane areas
Signals & Communication
- ONE designated signal person directs the operator; everyone else stays off the radio and out of the hand-signal sightline
- Anyone can give the STOP signal — that's the exception, and every worker should know it
- If the operator can't see the load's destination, signals or a spotter bridge the blind lift — never assumptions
- Riggers are qualified people; if you're not one, you don't hook, unhook, or adjust rigging
Taglines & Landing
- Taglines control load rotation and swing — hands on the tagline, never on the load
- Stay out of the pinch between a landing load and anything fixed: walls, stacks, rebar mats
- Land zones get cleared and cribbed before the load arrives, not while it hovers
Power Lines & Weather
- Minimum 20-foot clearance from energized lines for the crane and the load, unless a formal encroachment plan is in place
- If a crane contacts a line: stay away, warn others back, nobody touches the crane or the load — the ground itself can be energized
- Wind and monsoon gusts stop lifts; a swinging load in wind is nobody's argument to win
Key takeaways
- Never under the load, never in the swing radius
- One signal person — but anyone can call STOP
- Qualified riggers only touch rigging
- Taglines, not hands, control the load
- 20 feet from power lines, crane AND load
- Barricades mean it, even when the crane looks parked
Questions for your crew
- Never walk or stand under the load path, and stay out of the counterweight swing radius — barricaded or not.
- One designated signal person directs the operator — but anyone on site can give the STOP signal.
- Only qualified riggers hook, unhook, or adjust rigging.
- Control loads with taglines, never hands, and stay out of the pinch between a landing load and anything fixed.
- Keep the crane and the load at least 20 feet from power lines unless a formal encroachment plan is in place.
- If a crane contacts a line: stay away, warn others back, and let nobody touch the crane or the load.
Run this talk with crew sign-offs
This talk is part of the Safirst ONE toolbox talk library, in English and Spanish. Your foreman picks the talk in the app, the crew signs from their own phones by scanning a QR code, and the signed record files itself in your Docs Locker. Talk to Safirst to get it for your crews.